NEW QUESTION # 207
For natural gas pipe lines, each feel band in steel pipe must?

  • A. Have the longitude a weld as near as practical to the neutral axis of the band(49 CFR 192.313)
  • B. Latitude/longitude coordinates(CGA Best Practice 6.2)
  • C. Set of interrelated activities that use inputs to deliver an intended result(ISO 9000 3.4.1)
  • D. Part of quality management focused on fulfilling quality requirements(ISO 9000 3.3.7)

Answer: A


NEW QUESTION # 208
In the CGA Best Practice, an icon of a green square identifies
-On call center
-Facility Owner
-Designer
-Excavator

  • A. Facility Owner
  • B. Company
  • C. Excavator
  • D. Design Validation

Answer: C


NEW QUESTION # 209
The color for marking oil and gas buried lines

  • A. Blue
  • B. White
  • C. Green
  • D. Yellow

Answer: C


NEW QUESTION # 210
A type of cathodic protection

  • A. Pressure Testing
  • B. Impressed Current
  • C. Sacrificial Anodes
  • D. Quality Improvement

Answer: B


NEW QUESTION # 211
Typical gases used in new pipeline construction are?

  • A. Part of quality management focussed on setting quality objectives and specifying necessary operational processes, and resources to achieve the quality objectives(ISO 9000 3.3.5)
  • B. Within 2 feet of the existing facilities or the distance mandated by state law which ever is greater(INGAA CROSSING guide 11 K)
  • C. Set of interrelated activities that use inputs to deliver an intended result(ISO 9000 3.4.1)
  • D. Oxygen and acetylene (welding/cutting operations)Nitrogen (purging)LPG (heating/drying)Compressed air (pneumatic tools, grit blasting, tire inflation, painting)

Answer: D


NEW QUESTION # 212
Define Encroachment Area

  • A. Is the area where the ground disturbance occurs within 50 feet of the centerline of the existing facility or within the existing facilities ROW or easement, whichever is greater. Additional distance may be required for the constructions such as topography side-hill lays, catholic operating equipment, and topography.
  • B. Part of quality management focussed on providing confidence that quality requirements will be fulfilled.(ISO 9000 3.3.6)
  • C. A part of quality management Focused on the ability to fulfil quality requirements.The quality requirements can be related to any aspect such as effectiveness efficiency or traceability.
  • D. Set of interrelated activities that use inputs to deliver an intended result(ISO 9000 3.4.1)

Answer: D


NEW QUESTION # 213
Focused on providing confidence that quality requirements will be fulfilled.

  • A. Grading
  • B. Total quality management
  • C. Quality improvement
  • D. Quality assurance

Answer: D


NEW QUESTION # 214
Each gas service line must be buried with at least
18 in/private 24 in/street
12 in/private 18 in/street
24 in/private 36 in/street
18 in private/30 in / street

  • A. For the purpose of listing materials category
  • B. 12 inches of cover in private and 18 inches in street
  • C. Nominal wall thickness exceeds 1-1/4 inch
  • D. grind or sand the surface to bare metal prior to welding.

Answer: B


NEW QUESTION # 215
Flattening, sloping or other excavation to modify the terrain to make it safe and accessible for construction.

  • A. Grading
  • B. Clearing
  • C. Effectiveness
  • D. Testing

Answer: C


NEW QUESTION # 216
Work Permits for Confined Space Entry would be found under which OSHA standard?

  • A. OSHA 1910.119 (k) (29 CFR 1910) occupational safety and health standard
  • B. OSHA 1910.146 (29 CFR 1910) occupational safety and health standard
  • C. A spike test, strength test and/or a leak test(API 1110, 4.1.3 a)
  • D. Within a set of written process safety information controls(29 CFR 1910.119, general knowledge)

Answer: A


NEW QUESTION # 217
In regards to hazardous liquids onshore pipelines, pumping equipment must be installed on property that is under the control of the operator and at least_______ ft from the boundary of the pump station.

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: C


NEW QUESTION # 218
Color used for surveyed proposed excavation and centerline

  • A. Red
  • B. White
  • C. Green
  • D. Yellow

Answer: C


NEW QUESTION # 219
Define correct of action in terms related to action.

  • A. Action to illuminate the cause of a potential nonconformity or other potential undesirable situation.(Preventative action is taken to prevent occurrence were as correct of action is taken to prevent recurrence)(ISO 9000 3.12.1)
  • B. Part of quality management focussed on providing confidence that quality requirements will be fulfilled.(ISO 9000 3.3.6)
  • C. Is the singular point of contact identified within the company of the crossing company and the owner who has the responsibility to communicate about the safely managed crossing. There will be a cross and Company designated contact and an owner designated contact.
  • D. Action to illuminate the cause of a non-conformity in to prevent recurrence.(correct of action is taken to prevent recurrence where as preventative action is taken to prevent occurrence)(ISO 9000 3.12.2)

Answer: D


NEW QUESTION # 220
Inspections of excavation she,ll be conducted by competent person
a) Prior to the start of work
b) prior to the start of work and as needed throughout the shift and after every rainstorm that has an excess of 1 inch of rainfall or hazard increasing occurrence c) prior to the start of work and as needed throughout the shift and after every rainstorm that has in accidents of .5 inch of rain full or hazard increasing occurrence d) prior to the start of work and as needed throughout the shift and after every frame storm or hazard increasing occurrence

  • A. Owner operator
  • B. They shall be accepted as meeting the requirements provided they break at not less than 95% of the tensile strength of the material(API 1104 5.3)
  • C. A part of quality management Focused on the ability to fulfil quality requirements.The quality requirements can be related to any aspect such as effectiveness efficiency or traceability.
  • D. d) prior to the start of work and as needed throughout the shift and after every frame storm or hazard increasing occurrence(29 CFR 1926.651 (k) (I))

Answer: D


NEW QUESTION # 221
Permanent trench breakers cannot be installed within a ______________

  • A. Casing
  • B. Swamp-land
  • C. Wetland
  • D. Greenfield

Answer: B


NEW QUESTION # 222
Cathodic protection test stations are typically installed every?

  • A. rework(api 1104 3.1.25)
  • B. 12 inches(api 1169 7.15)
  • C. 2 to 3 kilometres(CEPA 16.1)
  • D. 98 to 3 kilometres(cepa 16.1)

Answer: C


NEW QUESTION # 223
During a pressure test, the pressure recorders and deadweight gauge shall be located at a safe distance at least_______ from the facility tested.

  • A. 50 ft
  • B. 100 ft
  • C. 500 ft
  • D. 200 ft

Answer: B


NEW QUESTION # 224
Trench Boxes must extend ____above outside soil level

  • A. 12"
  • B. 24"
  • C. 18"
  • D. 25,

Answer: C


NEW QUESTION # 225
Ensuring that the _______________ will not cause erosion or direct water into sensitive environmental resource areas, including cultural resource sites, wetlands, waterbodies, and sensitive species habitats;

  • A. calibration
  • B. required reporting
  • C. design of slope breakers
  • D. design validation

Answer: C